Pass of Birnam to Tay Crossing has another public event to look at the whole route options on 16 and 17 May 2019
https://www.transport.gov.scot/news/dro ... g-options/
More DPEA updates:
Tay Crossing to Ballinluig a reporter has been appointed and 1 of the 18 objections has been withdrawn.
Killiecrankie to Glen Garry also has a reporter (same reporter as the Tay Crossing to Ballinluig interestingly) and 4 of the 188 objections have been withdrawn (Cairngorm National Park Authority objection being a significant withdrawal though).
Tomatin to Moy reporter has suggested Pre-Enquiry meeting will be in early June but no date set yet.
Dalwhinnie to Crubenmore the remaining landowner objections are withdrawn so the hearing session on 11 June won't take place. SSE remain as a statutory objector but negotiations ongoing with 12 June hearing session date set if agreement can't be reached.
Complete
A9 Kincraig - Dalraddy (September 2017)
Under Construction
A9 Luncarty - Pass of Birnam (February 2019)
Contract Let
none
Procurement Underway
none
Made Orders Published
none
Public Local Inquiry (PLI) report with Ministers
A9 Glen Garry to Dalwhinnie (February 2019)
https://www.dpea.scotland.gov.uk/CaseDe ... ?ID=119863
2 objections (1 statutory landowner, 1 non-statutory) being dealt with by written submission.
Public Local Inquiry (PLI) report being written
A9 Pitlochry to Killiecrankie (March 2019)
https://www.dpea.scotland.gov.uk/CaseDe ... ?ID=119865
2 objections (1 statutory landowner, 1 non-statutory) being dealt with by written submission.
Public Local Inquiry (PLI) Hearing sessions date set
A9 Dalwhinnie to Crubenmore (June 2019)
https://www.dpea.scotland.gov.uk/CaseDe ... ?ID=120011
Reporter appointed Jan 19. 2 objections remain, 1 utility, 1 non statutory (Transform Scotland).
Landowner objections withdrawn May 2019. SSE objection partially withdrawn March 2019. Inquiry date proposed for 12 June, may be that all except Transform Scotland withdraw objections leading to cancellation of hearing.
Public Local Inquiry (PLI) pre-inquiry meeting occurred
None
Public Local Inquiry (PLI) ordered
A9 Tomatin to Moy (January 2019)
https://www.dpea.scotland.gov.uk/CaseDe ... ?id=120174
Reporter appointed March 2019. 11 objections remain, 8 landowners, 2 utility, 1 non statutory (Transform Scotland).
A9 Killiecrankie to Glen Garry (March 2019) -
https://www.dpea.scotland.gov.uk/CaseDe ... ?ID=120283
Reporter appointed April 2019. 189 objections remain, 17 statutory and 171 non statutory.
A9 Tay Crossing to Ballinluig (March 2019) -
https://www.dpea.scotland.gov.uk/CaseDe ... ?ID=120312
Reporter appointed April 2019. 18 objections remain, 9 statutory and 9 non statutory.
Dalraddy to Slochd and Crubenmore to Kincraig expected to be going to PLI in "Spring 2019" in TS letter to Network Rail from October 2018.
Draft Orders published - Exhibition feedback published
A9 Dalraddy to Slochd (September 2018) -
Exhibition responses published October 2018
Draft Orders published - Exhibition held
A9 Crubenmore to Kincraig (October 2018) -
https://www.transport.gov.scot/publicat ... -dualling/
Draft Orders published
none
DMRB Stage 3 exhibition held (Interim detailed design consultation)
none
DMRB Stage 2 (Preferred Route) designs published
none
Pre Stage 2 Route Design Options exhibition
A9 Pass of Birnam to Tay Crossing (March 2019)-
https://www.transport.gov.scot/publicat ... -dualling/
Construction Time Estimates:
Luncarty - Pass of Birnam - 22 months
Tay Crossing to Ballinluig 2 - 2.5 years
Pitlochry to Killiecrankie 3 - 3.5 years
Killiecrankie to Glen Garry 3 - 3.5 years
Glen Garry to Dalwhinnie and Dalwhinnie to Crubenmore 3 - 3.5 years
Crubenmore - Kincraig 3.5 years
Dalraddy to Slochd 4.5 years
Tomatin to Moy 2.5 - 3 years