M1 J13-16 ALR smart motorway

The study of British and Irish roads - their construction, numbering, history, mapping, past and future official roads proposals and general roads musings.

There is a separate forum for Street Furniture (traffic lights, street lights, road signs etc).

Registered users get access to other forums including discussions about other forms of transport, driving, fantasy roads and wishlists, and roads quizzes.

Moderator: Site Management Team

User avatar
M4 Cardiff
Member
Posts: 2186
Joined: Mon Sep 20, 2004 15:12
Location: Leamington Spa

Re: M1 J13-16 ALR smart motorway

Post by M4 Cardiff » Mon Sep 14, 2020 13:34

Is anyone here interested in geology? It is fascinating to observe the new cuts through the soils all the way along this section.
Driving thrombosis caused this accident......a clot behind the wheel.

M19
Member
Posts: 2106
Joined: Mon Dec 24, 2001 05:00
Location: Rothwell, Northants

Re: M1 J13-16 ALR smart motorway

Post by M19 » Mon Sep 14, 2020 19:56

I hope so, it’s taken two years so far.

I’m so glad to be working from home now instead of commuting that route.
M19

User avatar
EpicChef
Forum Moderator
Posts: 1865
Joined: Wed Aug 03, 2016 11:47
Location: London, UK

Re: M1 J13-16 ALR smart motorway

Post by EpicChef » Tue Jan 12, 2021 16:49

Any updates on this project?

HE website doesn’t display any updates since the 18th May.
Did you know there's more to SABRE than just the Forums?
Add your roads knowledge to the SABRE Wiki today!
Have you browsed SABRE Maps recently? Try getting involved!

Nader
Member
Posts: 277
Joined: Tue Mar 22, 2011 14:10
Location: Milton Keynes

Re: M1 J13-16 ALR smart motorway

Post by Nader » Wed Jan 13, 2021 11:02

Been a while since I last ventured onto the M1, but from the occasions I have run on footbridges crossing it, as far as I can see J13-14 is basically complete, with 14-15 not far behind.

There's a nice long footpath at the top of a bank that runs basically alongside the motorway just south of J14 for half a mile, I'll try and run along it in daylight hours at some point to get a better idea of what is going on.

fras
Member
Posts: 2386
Joined: Tue Apr 10, 2012 18:34

Re: M1 J13-16 ALR smart motorway

Post by fras » Wed Jan 13, 2021 12:55

EpicChef wrote:
Tue Jan 12, 2021 16:49
Any updates on this project?

HE website doesn’t display any updates since the 18th May.
I passed this way late last year, round about November, and the "Progress Sign" stated it would be complete in 20 months. Like a lot of contractors, I suspect the very wet weather in autumn, plus Covid19 strictures have delayed the project. For instance the Congleton Link Road was originally expected to open Late-2020, but now shows Spring 2021.

User avatar
EpicChef
Forum Moderator
Posts: 1865
Joined: Wed Aug 03, 2016 11:47
Location: London, UK

Re: M1 J13-16 ALR smart motorway

Post by EpicChef » Wed Jan 13, 2021 12:58

fras wrote:
Wed Jan 13, 2021 12:55
EpicChef wrote:
Tue Jan 12, 2021 16:49
Any updates on this project?

HE website doesn’t display any updates since the 18th May.
I passed this way late last year, round about November, and the "Progress Sign" stated it would be complete in 20 months. Like a lot of contractors, I suspect the very wet weather in autumn, plus Covid19 strictures have delayed the project. For instance the Congleton Link Road was originally expected to open Late-2020, but now shows Spring 2021.
That's summer 2022 - around the expected date of completion.
Did you know there's more to SABRE than just the Forums?
Add your roads knowledge to the SABRE Wiki today!
Have you browsed SABRE Maps recently? Try getting involved!

fras
Member
Posts: 2386
Joined: Tue Apr 10, 2012 18:34

Re: M1 J13-16 ALR smart motorway

Post by fras » Wed Jan 13, 2021 13:02

EpicChef wrote:
Wed Jan 13, 2021 12:58
fras wrote:
Wed Jan 13, 2021 12:55
EpicChef wrote:
Tue Jan 12, 2021 16:49
Any updates on this project?

HE website doesn’t display any updates since the 18th May.
I passed this way late last year, round about November, and the "Progress Sign" stated it would be complete in 20 months. Like a lot of contractors, I suspect the very wet weather in autumn, plus Covid19 strictures have delayed the project. For instance the Congleton Link Road was originally expected to open Late-2020, but now shows Spring 2021.
That's summer 2022 - around the expected date of completion.
So it's not delayed, or the sign isn't being updated as well as the website !

Duple
Member
Posts: 109
Joined: Fri Apr 10, 2015 21:58

Re: M1 J13-16 ALR smart motorway

Post by Duple » Sun Jan 17, 2021 20:58

fras wrote:
Wed Jan 13, 2021 12:55
EpicChef wrote:
Tue Jan 12, 2021 16:49
Any updates on this project?

HE website doesn’t display any updates since the 18th May.
I passed this way late last year, round about November, and the "Progress Sign" stated it would be complete in 20 months. Like a lot of contractors, I suspect the very wet weather in autumn, plus Covid19 strictures have delayed the project. For instance the Congleton Link Road was originally expected to open Late-2020, but now shows Spring 2021.
Slightly OT but the Congleton Link Road has been delayed because of water table issues, I don't doubt covid hasn't helped, but they have done a lot of unplanned work.