M8 Completion Approved

The study of British and Irish roads - their construction, numbering, history, mapping, past and future official roads proposals and general roads musings.

There is a separate forum for Street Furniture (traffic lights, street lights, road signs etc).

Registered users get access to other forums including discussions about other forms of transport, driving, fantasy roads and wishlists, and roads quizzes.

Moderator: Site Management Team

Post Reply
User avatar
michael769
Member
Posts: 11413
Joined: Mon May 30, 2005 20:36
Location: Polbeth, West Lothian
Contact:

Re: M8 Completion Approved

Post by michael769 »

Work to start on £500m M8, M73 and M74 motorway upgrades

Work is set to get underway on a £500m project to upgrade the motorway network in central Scotland.

The Scots Roads Partnership (SRP) will carry out the advance works ahead of signing a contract with Transport Scotland for the full job next month.

The upgrade work will see the six-mile "missing link" completed on the M8 in North Lanarkshire.

Improvements to the Raith Interchange and widening of key sections of the M8, M73 and M74 are also part of the plan.

The work will see upgrading of the M8 between Baillieston and Newhouse to motorway standard.

This will require upgrades to the connections to the M73 motorway at Baillieston and a new junction at Shawhead, which will connect to the A725 East Kilbride road.
http://www.bbc.co.uk/news/uk-scotland-g ... t-25944134
Minds are like parachutes - they only function when open
Thomas Robert Dewar(1864-1930)
Take the pledge
User avatar
wrinkly
Member
Posts: 8986
Joined: Tue Mar 04, 2008 12:17
Location: Leeds

Re: M8 Completion Approved

Post by wrinkly »

User avatar
wrinkly
Member
Posts: 8986
Joined: Tue Mar 04, 2008 12:17
Location: Leeds

Re: M8 Completion Approved

Post by wrinkly »

Parliamentary answer at the bottom of this page.
m80
Member
Posts: 255
Joined: Sat Nov 20, 2010 12:38

Re: M8 Completion Approved

Post by m80 »

wrinkly wrote:Parliamentary answer at the bottom of this page.
"..construction cost of approximately £310 million; significantly below the pre-tender estimate of £415 million.."

Good result. I wonder if the money saved will enable them to accelerate some other road schemes like A9 dualling.
User avatar
ScottB5411
Member
Posts: 4153
Joined: Wed Jun 16, 2010 20:04
Location: St. Louis, Missouri, USA

Re: M8 Completion Approved

Post by ScottB5411 »

It does make me wonder if some things have been cut back on though, that's a fairly hefty saving
How about some more beans Mr. Taggart?
User avatar
IAN
Member
Posts: 1494
Joined: Thu Dec 20, 2001 19:07

Re: M8 Completion Approved

Post by IAN »

It looks like this project has passed the 'point of no return'. Has anyone any idea what the latest stage was that a road project was cancelled, or have any projects ever been cancelled after construction has commenced?

Ian (M5 Driver)
AKA M5 Driver
User avatar
Bryn666
Elected Committee Member
Posts: 35754
Joined: Thu Jun 20, 2002 20:54
Contact:

Re: M8 Completion Approved

Post by Bryn666 »

Google "Goat Path Expressway" ;-)
Bryn
Terminally cynical, unimpressed, and nearly Middle Age already.
She said life was like a motorway; dull, grey, and long.

Blog - https://showmeasign.online/
X - https://twitter.com/ShowMeASignBryn
YouTube - https://www.youtube.com/@BrynBuck
Nwallace
Member
Posts: 4239
Joined: Tue Apr 10, 2007 22:42
Location: Dundee

Re: M8 Completion Approved

Post by Nwallace »

IAN wrote:It looks like this project has passed the 'point of no return'. Has anyone any idea what the latest stage was that a road project was cancelled, or have any projects ever been cancelled after construction has commenced?

Ian (M5 Driver)
Not road but GARL...
m80
Member
Posts: 255
Joined: Sat Nov 20, 2010 12:38

Re: M8 Completion Approved

Post by m80 »

Nwallace wrote:
IAN wrote:It looks like this project has passed the 'point of no return'. Has anyone any idea what the latest stage was that a road project was cancelled, or have any projects ever been cancelled after construction has commenced?

Ian (M5 Driver)
Not road but GARL...
GARL didn't get to construction stage, it was cancelled during procurement.
User avatar
A8000Bob
Member
Posts: 3156
Joined: Sat Jan 29, 2005 20:02
Location: Kirkcaldy, Fife

Re: M8 Completion Approved

Post by A8000Bob »

A801 bypass of Avon Gorge.
User avatar
owen b
Member
Posts: 9859
Joined: Sun Mar 16, 2003 15:22
Location: Luton

Re: M8 Completion Approved

Post by owen b »

IAN wrote:It looks like this project has passed the 'point of no return'. Has anyone any idea what the latest stage was that a road project was cancelled, or have any projects ever been cancelled after construction has commenced?
The A20 Ashford bypass was under construction at the start of WW2. It didn't restart until several years post war.
Owen
User avatar
wrinkly
Member
Posts: 8986
Joined: Tue Mar 04, 2008 12:17
Location: Leeds

Re: M8 Completion Approved

Post by wrinkly »

A8000Bob wrote:A801 bypass of Avon Gorge.
Another hoary myth resurfaces.
User avatar
A8000Bob
Member
Posts: 3156
Joined: Sat Jan 29, 2005 20:02
Location: Kirkcaldy, Fife

Re: M8 Completion Approved

Post by A8000Bob »

wrinkly wrote:
A8000Bob wrote:A801 bypass of Avon Gorge.
Another hoary myth resurfaces.
?
User avatar
wrinkly
Member
Posts: 8986
Joined: Tue Mar 04, 2008 12:17
Location: Leeds

Re: M8 Completion Approved

Post by wrinkly »

A8000Bob wrote:
?
I've seen previous discussions of this but I've never seen any evidence that any design for the missing section of the A801 was ever completed, or that any contract to build it was ever advertised, let alone cancelled after work had started. As far as I know the only evidence we have is some advance earthworks, which may have been done partly to provide fill for an adjacent section.

Edit: I suppose it's a question of how you interpret the terms in Ian's question. I was taking it to mean contracts cancelled after work had started. If you interpret "project" in a larger sense, there are probably quite a lot that have been cancelled (or grossly postponed) after some preparatory work has been done on the ground.
Last edited by wrinkly on Sun Feb 02, 2014 21:39, edited 1 time in total.
User avatar
Gav
Member
Posts: 1968
Joined: Sat Oct 22, 2005 17:44

Re: M8 Completion Approved

Post by Gav »

It may be that the erathworks was part of the contract back then to grade it and prep it for the next stage.
User avatar
A935
Member
Posts: 505
Joined: Sun Nov 27, 2005 01:08
Location: Dundee-ish

Re: M8 Completion Approved

Post by A935 »

m80 wrote:
Nwallace wrote:
IAN wrote:It looks like this project has passed the 'point of no return'. Has anyone any idea what the latest stage was that a road project was cancelled, or have any projects ever been cancelled after construction has commenced?

Ian (M5 Driver)
Not road but GARL...
GARL didn't get to construction stage, it was cancelled during procurement.
I have signalling scheme plans for GARL in my archive at work, so it got to at least GRIP 4 or 5. And PCI was obviously a major part of the overall scheme which did get completed.
User avatar
nirs
Member
Posts: 3915
Joined: Thu Dec 14, 2006 14:51
Location: Belfast, Northern Ireland
Contact:

M8 Completion Approved

Post by nirs »

Construction actually began on Phase 1 of the Belfast Urban Motorway in 1973 (piling for the elevated section at the north end) but had to be halted shortly after due to civil disorder. The scheme was subsequently cancelled.

Speaking of which: http://www.colourpointbooks.co.uk/more_ ... hp?id=1806

(Whistles nonchalantly)
Northern Ireland Roads Site www.wesleyjohnston.com/roads
m80
Member
Posts: 255
Joined: Sat Nov 20, 2010 12:38

Re: M8 Completion Approved

Post by m80 »

No going back now:


"Transport Scotland has announced that the £500million deal to construct the new M8 and make improvements to the M73 and M74 was officially finalised today (Thursday, February 20.)"

http://www.transportscotland.gov.uk/New ... ts-project
User avatar
A72
Member
Posts: 787
Joined: Fri Jul 20, 2012 17:21
Location: Newtown St Boswells, Scottish Borders

Re: M8 Completion Approved

Post by A72 »

m80 wrote:No going back now:


"Transport Scotland has announced that the £500million deal to construct the new M8 and make improvements to the M73 and M74 was officially finalised today (Thursday, February 20.)"

http://www.transportscotland.gov.uk/New ... ts-project
And about time, too!

What was the reason for the gap, in the first place? It's always baffled me that the M8 was never built as a continuous motorway.
The 7-Zone Challenge
A roads: 71/71
B roads: 181/181
Total: 252/252

Completed: 04/11/20.
chris486
Account deactivated at user request
Posts: 2939
Joined: Sat Sep 05, 2009 10:22
Location: n/a

Re: M8 Completion Approved

Post by chris486 »

A72 wrote:
What was the reason for the gap, in the first place? It's always baffled me that the M8 was never built as a continuous motorway.
Like most motorways it was built as a series of bypasses which gradually becamed conjoined.

Because the final gap in the motorway was/is fully grade separated, it was left until last.
..