Construction Start Date | |||
October 2014 | |||
Opening Date | |||
July 2016 | |||
Official Opening | |||
28 July 2016 | |||
Cost | |||
£9.5 million | |||
Contractor | |||
Balfour Beatty | |||
For the London to Inverness trunk road, which also ran through Derby, see T12 (Britain).
The T12 Link Road is a new road between Chellaston and Sinfin. Its main purpose is to allow access to a new development in the area. The name comes from the number of the policy which proposed it. It is not currently known if the route will be numbered.
Route
The T12 Link Road is a continuation of Holmleigh Way in Chellaston, which was originally built with the purpose of linking Chellaston to Sinfin. The road begins at the existing roundabout at the end of Holmleigh Way. It then continues across one roundabout which will give access to the developments, before reaching another roundabout where it TOTSOs. It then terminates on Wilmore Road, near Rolls-Royce, at a traffic signal controlled junction. The link road also allows easier access for large vehicles to Rolls Royce from the A50.
Construction
Balfour Beatty were appointed to construct the link road at the end of October 2014, with works commencing shortly afterwards. The link road was completed around July 2016.